Orange County sets a December 1, 2026 public hearing on a temporary moratorium on data-center applications
Takes effect Dec 1, 2026 · Upcoming · A proposal until the board votes. The hearing date could change, and the draft leaves the moratorium's start date blank.
Verified
4 sources listed; last checked Nov 15, 2026.
What changed
Orange County commissioners have a public hearing on their December 1, 2026 agenda on an ordinance "Establishing a temporary moratorium within the unincorporated area of Orange County, Florida, on the acceptance, processing, and review of applications and County approvals for certain data centers and associated facilities" (the title goes on), according to the Clerk of the Board's page for File 26-1371. It is a proposal. The same page shows no action by the board yet, and a draft of the ordinance leaves its effective date blank.
What changed
- A hearing is on the agenda. The Clerk of the Board's page lists File 26-1371 as a public hearing, on the agenda for December 1, 2026, covering all districts. The file was created on 10/30/2026 and is in the control of the Planning, Environmental, and Development Services Department. The staff memo on the page is dated October 28, 2026.
- No vote has been taken. The page's history shows 0 records and its final action is blank. The board's data feed for the same file gives no passed date and no enactment date.
- What the draft would pause. A draft ordinance attached to the file, marked as a draft of October 7, 2026, says that during the moratorium the county would not accept, process, review, approve or issue any application or county approval for a data center facility, apart from the exceptions it lists. The approvals it names include rezonings, site plans, building permits and plat approvals.
- What counts as a data center. The draft defines one as a building, part of a building or group of buildings that mainly houses computer systems used to store, process or transmit digital information. It names artificial intelligence computing, cloud computing and cryptocurrency mining among the uses covered.
- How long. The draft sets the length at "twelve (12)" months "from the effective date of this Ordinance, unless earlier terminated by the Board." (the two quotations are parts of one sentence). It adds, as part of a longer sentence, that "The Board may extend the moratorium by subsequent ordinance if it finds that additional time is necessary" to complete the research, public review and adoption of regulations.
- Exceptions in the draft. The moratorium would not apply to server or computer rooms that are incidental to another lawful use; to facilities whose total anticipated electrical load at full buildout "does not exceed twenty megawatts (20 MW)" (part of a longer sentence), which the applicant would have to prove; to ordinary repair and maintenance of existing lawful facilities; to life-safety work; to certain government facilities; or to vested rights. The board could also allow a specific application to be processed after a public hearing.
- Applications already filed. The draft would also cover an application submitted before the effective date if the approval it seeks had not been finally issued by that date.
When
- Public hearing: on the board's agenda for December 1, 2026. This is scheduled, not done, and the date could change.
- Start of the moratorium: not set. The draft leaves its effective date blank.
- Length: twelve months from that effective date in the draft, unless the board ends it earlier or extends it.
Where
Unincorporated Orange County only. The draft says the ordinance applies only within the unincorporated area, so land inside city limits is not covered.
Where the sources differ
- On the length. Orlando Weekly, a news report dated September 16, 2026 and updated September 23, 2026, reported on a board discussion: "Commissioners reached a consensus for a six- to 18-month moratorium, depending how long county staff need to research potential impacts." The county's draft says twelve months. This post goes by the draft, because it is the county's own document and is dated after the news report. The draft is not final, and the board could change the length before or at the hearing.
- On the vote. Orlando Weekly reported that a vote was expected at the board's December 1 meeting. The county's page calls the item a public hearing on that date and does not say a vote will be taken.
What it means if you live here
- Nothing is paused yet. Until the board adopts an ordinance and it takes effect, no moratorium applies.
- If you want to be heard, the public hearing is the board's scheduled occasion for it. Check the Clerk of the Board's page for the file before going, since the date could change.
- If you plan a data center in the unincorporated county, the draft would stop new applications, and pending ones not finally approved, for facilities above 20 megawatts.
- What this post did not read. The other attachments to the file, including the request file and the proof of publication, were not read. The version of the ordinance put before the board may differ from the October 7, 2026 draft.
Sources
- Orange County Comptroller, Clerk of the Board, File 26-1371, public hearing on agenda 12/1/2026
- Orange County, draft ordinance attached to File 26-1371, marked DRAFT 10/07/2026
- Orange County Comptroller, Clerk of the Board, File 26-1371 in the board records data feed
- Orlando Weekly, McKenna Schueler, September 16, 2026, updated September 23, 2026 (news report)
Last checked Nov 15, 2026.