Construction begins on the RoseArts District on the former Lake Orlando golf course
In effect since Sep 30, 2026 · In effect
What changed
BeforeThe closed Lake Orlando golf course, approved for redevelopment as the RoseArts District in December 2021.
NowConstruction underway on Phase 1: about 1,600 apartments in four buildings, 160 designated affordable; the first building about 30 months from the September 30, 2026 groundbreaking, per the developer.
What it means if you live here
- No apartments to rent yet. The developer puts the first building at about 30 months from the September 30, 2026 groundbreaking, which by that estimate means around spring 2029.
- More phases are planned. At full buildout the City's page lists "5,650 multifamily dwelling units", "350,000 square feet of commercial development" and "Up to 65-acres of parks and green space".
- On traffic, WFTV reported the developer is "building its own road to facilitate and accommodate the traffic".
Construction has started on the RoseArts District, the planned apartment-and-retail district on the former Lake Orlando golf course in Rosemont. The City of Orlando's project page records "September 30, 2026 – Groundbreaking on phase 1". Westside Capital Group broke ground that Wednesday with Mayor Buddy Dyer, WFTV reported.
What changed
- Phase 1 is under way. The City's page describes it as "+/- 1,594 residential units with 160 units affordable". The City's Phase 1 letter allows "up to 1,600 residential units and up to 150,000 sq. ft. of non-residential uses to be in four multi-story buildings".
- "Affordable" means designated in the approved plan, not certified. A 2024 City letter says "The overall project has not been approved for Affordable Housing Certification".
- A charter school, per WFTV. WFTV reported that the phase "is also expected to include up to 150,000 square feet of retail space and a charter school". The City's page does not mention a school.
- The cost is a reported figure, not a settled one. WFTV headlined "$2.6 billion", and GrowthSpotter reported the same figure. A second WFTV report the same day headlined "$1-2 billion".
- GrowthSpotter called it the largest infill development in Orlando's history.
When
- Groundbreaking: Wednesday, September 30, 2026.
- The first building: about 30 months, per the developer. A GrowthSpotter photo caption reports that Westside Capital's Jakub Hejl said the first building in Phase 1 would take about 30 months to build. That is the developer's estimate, not a commitment.
- How it got here: the City Council adopted the RoseArts master plan by "Ordinance No. 2021-74" in December 2021, and approved the Phase 1 plan in 2022.
Where
- The whole site is the City's "phased redevelopment of 128-acres formerly the home of the Lake Orlando Golf Course & Country Club".
- Phase 1 is "+/- 38.5 acres located south of Rosamond Drive".
Sources
- City of Orlando, Lake Orlando RoseArts District project page
- City of Orlando, Phase 1 letter of determination
- WFTV Channel 9, September 30, 2026
- WFTV Channel 9, September 30, 2026 (second report)
- FOX 35 Orlando, September 30, 2026
- GrowthSpotter (Orlando Sentinel), September 30, 2026
Updated Oct 6, 2026.
Updates and corrections
- November 9, 2026: two quotations from GrowthSpotter's September 30, 2026 story (the description of the project as the largest infill development in Orlando history, and the developer's estimate for the first building) are now paraphrases, with the story still cited. We do not hold those words from any other source. The facts and the link are unchanged.