Did Kissimmee widen Thacker Avenue by June 2025, as promised?

The Roadmap Reckoner · updated 2026-10-30

PENDING, OVERDUE by about 16 months

What happenedNot complete: still listed under Capital Projects (5-Yr Plan) in the city's Aug. 25, 2026 budget; no construction contract award found in 36 months of Commission records; the state's $250,000 was vetoed
Promised2025-06-30 (construction "7/1/2024" to "6/30/2025", the city's Jan. 2024 request to the Florida Senate)
Who promisedCity of Kissimmee
WhereKissimmee, Florida (Thacker Avenue, between Flora Boulevard and Osceola Parkway)

Verdict: PENDING, OVERDUE, by about 16 months. In January 2024 the City of Kissimmee asked the state to help pay for "the remaining two lanes of an important collector road within the city, Thacker Avenue" [1], with construction to start on "7/1/2024" [1] and finish by "6/30/2025" [1]. On August 25, 2026, the city's budget still listed "Thacker Ave Widening" under "Capital Projects (5-Yr Plan)" [8]. In the City Commission's published agenda outlines and minutes for its 118 meetings over three years, we found no award of a construction contract for the widening. The state money the city asked for did not arrive: the Legislature appropriated $250,000 of the $500,000 requested [2, 4], and that line is on the Governor's veto list [5].

The promise

The City of Kissimmee's request to the Florida Senate, Local Funding Initiative Request #3330 for fiscal year 2024-25, "Date of Request 01/10/2024" [1]:

"In an effort to keep up with the unprecedented growth in the region, the City of Kissimmee seeks funding to construct the remaining two lanes of an important collector road within the city, Thacker Avenue. This is an important connection to one of the major arterial roads within the city, Osceola Parkway. In addition to increasing capacity by constructing two lanes, the project will add two signalized intersections, improve stormwater drainage, and add sidewalks to improve pedestrian connectivity in an area with two elementary schools, retail centers, and thousands of residential and multifamily units." [1]

The same request gave the dates: "What is the estimated start date of construction? 7/1/2024" [1] and "What is the estimated completion date of construction? 6/30/2025" [1]. On the money, it said: "the city is in need of additional funding to complete this $7 million project. The city currently has $6.5 million budgeted in its CIP." [1]

Timeline

What changed, and why

What it cost

What is still open

Sources

  1. 1. flsenate.gov › FY2024 25 S3330
  2. 2. kissimmeefl.api.civicclerk.com › GetMeetingFileStream(fileId=7374,plainText=false)
  3. 3. kissimmeefl.api.civicclerk.com › GetMeetingFileStream(fileId=7461,plainText=false)
  4. 4. flsenate.gov › PDF
  5. 5. flcourts-media.flcourts.gov › FY 2024 25 Veto List
  6. 6. kissimmeefl.api.civicclerk.com › GetMeetingFileStream(fileId=7834,plainText=false)
  7. 7. kissimmeefl.api.civicclerk.com › GetMeetingFileStream(fileId=8376,plainText=false)
  8. 8. kissimmeefl.api.civicclerk.com › GetMeetingFileStream(fileId=11097,plainText=false)
  9. 9. kissimmee.gov › Projects
  10. 10. kissimmee.gov › Engineering
  11. 11. kissimmeefl.api.civicclerk.com › GetMeetingFileStream(fileId=11181,plainText=false)
  12. 12. kissimmeefl.api.civicclerk.com › GetMeetingFileStream(fileId=11194,plainText=false)

Updates and corrections

Re-checked October 30, 2026. The City Commission has met once since this page's previous update, on October 20, 2026 [11], and the minutes of its October 6 meeting are now posted [12]. Thacker Avenue is not an item in either meeting's record: it appears nowhere in the October 20 agenda and its 324-page packet, or in the October 6 minutes. The city's Projects list still shows "13 Result(s) Found", and the widening is on neither of its two pages [9]. The Engineering Division page does not mention it [10]. As of October 30, 2026, we had seen no newer news of the widening. The verdict is unchanged; the delay is counted to October 30, 2026.