The Roadmap Reckoner

Public promises checked against the public record: what was promised, by whom, for when, and what was actually delivered. The scorecard shows who keeps their commitments; the tracker lists every promise; each entry below has the full write-up, with every claim linked to its source.

Scorecard Tracker Entries

Scorecard: who keeps their commitments

18promises checked
0on time
3late
0smaller
0abandoned
10overdue
5on track
RankPromiserRecordOn timeLateSmallerAbandonedOverdueOn trackKept on timeOf decided
Too few decided promises to rank yet (under 3)
—City of Orlando0000200%0 of 2 decided
—Central Florida Commuter Rail Commission (Orange, Osceola, Seminole, Volusia, Orlando) and FDOT0000100%0 of 1 decided
—City of Kissimmee0000100%0 of 1 decided
—Florida Department of Transportation (FDOT), with its concessionaire I-4 Mobility Partners0100000%0 of 1 decided
—Greater Orlando Aviation Authority (GOAA)0000100%0 of 1 decided
—Mayor Buddy Dyer, City of Orlando0000100%0 of 1 decided
—Orange County Library System0100000%0 of 1 decided
—Orlando Housing Authority (OHA), in its Moving to Work Annual Plans to HUD; partner: City of Orlando Community Redevelopment Agency0000100%0 of 1 decided
—Orlando Utilities Commission (OUC), Board of Commissioners0000100%0 of 1 decided
—Osceola County0000100%0 of 1 decided
—SED Development, JMA Ventures and Machete Group (the developers), with the Orlando Magic0000100%0 of 1 decided
—Seminole County (Seminole County Fire Department)0100000%0 of 1 decided
—AdventHealth (for AdventHealth Winter Garden)000001—0 of 0 decided
—Central Florida Expressway Authority (CFX)000001—0 of 0 decided
—Orange County Government (Mayor Jerry L. Demings's Housing for All Task Force; accepted by the Board of County Commissioners)000001—0 of 0 decided
—Orange County, Florida, through the Orange County Convention Center (OCCC)000001—0 of 0 decided
—The Walt Disney Company (Disney Experiences and Walt Disney Imagineering)000001—0 of 0 decided

How the rank works. Kept on time = promises delivered on time ÷ decided promises. Decided means delivered (on time, late or smaller), abandoned, or overdue; a promise still on track is not counted either way. A promiser is ranked once it has 3 or more decided promises; ties go to the one with more. Every number here can be recounted from the tracker below.

Every promise, tracked

18 promises checked against the public record.

PromisePromiserPlace VerdictPromisedDelivered / status Last checked
Did Central Florida's local governments take over SunRail by June 30, 2024, as promised?Central Florida Commuter Rail Commission (Orange, Osceola, Seminole, Volusia, Orlando) and FDOTOrlando metro, FloridaPENDING, OVERDUE
by about 2 years 3 months
2024-06-30Funding: taken over 2025-01-01 (6 months late). Operations: still run by FDOT; deadline 2027-12-312026-09-25
Did Orlando start building The Canopy, its public space under I-4, in early 2025 as promised?City of OrlandoOrlando, FloridaPENDING, OVERDUE
by about a year and a half
2025-03-31 ("early 2025")Not started; the City still expects construction to begin in fall 2026, and its third-quarter 2026 start date has passed2026-10-12
Was a permanent Pulse memorial in place by June 12, 2026, the ten-year remembrance, as Orlando's mayor said he wanted?Mayor Buddy Dyer, City of OrlandoOrlando, FloridaPENDING, OVERDUE
by three months and 15 days
2026-06-12 (the ten-year remembrance)Not built; the City now expects construction to begin in September 2026 and completion in late 20272026-09-27
Did Orlando finish its Southeast Community and Government Center by spring 2026, as promised?City of OrlandoOrlando, FloridaPENDING, OVERDUE
by about four months
2026-06-20 ("by spring 2026")Not complete; still under construction, and the City's project page still gives the third quarter of 2026, which ended September 302026-10-12
Did OUC retire its Stanton Unit 1 coal plant by 2025, as its board voted in 2021?Orlando Utilities Commission (OUC), Board of CommissionersOrlando, FloridaPENDING, OVERDUE
by eight months and 28 days
2025-12-31 ("by no later than 2025"; the 2022 plan's December 31, 2025 shutdown date)Not retired or placed in cold shutdown; a U.S. DOE order keeps Unit 1 available for operation through November 30, 20262026-09-28
Is Orange County's $560 million convention center expansion on course to finish in 2029, as promised?Orange County, Florida, through the Orange County Convention Center (OCCC)Orlando, Florida (International Drive)PENDING, ON TRACK2029 (finish; construction to begin in 2026, per the OCCC's March 27, 2025 release)Not yet due; construction green-lit March 2026, county still states a late-2029 opening at $559.7 million2026-09-29
Is CFX on course to build the Poinciana Parkway extension in the time it promised in 2024?Central Florida Expressway Authority (CFX)Poinciana, Osceola County, Florida (Orlando metro)PENDING, ON TRACK"Through year eight of the fifteen-year planning period" (May 2024 work-plan release; no calendar year named; FY 2032 on the entry's count)Not yet due; CFX's project page gives construction beginning mid-2027 and completion estimated mid-2030; no construction contract found2026-09-30
Will downtown Orlando's Westcourt district be complete by March 2027, as its developers promised in 2024?SED Development, JMA Ventures and Machete Group (the developers), with the Orlando MagicDowntown Orlando, Florida (the block beside the Kia Center)PENDING, OVERDUEGroundbreaking late 2024; completion by March 2027 (developers' April 2024 release)Not started: none of six City of Orlando permit applications issued (all Open); a developer now cites 2028 delivery2026-10-01
Is Orange County putting the $160 million it promised in 2019 into its affordable housing trust fund?Orange County Government (Mayor Jerry L. Demings's Housing for All Task Force; accepted by the Board of County Commissioners)Orange County, FloridaPENDING, ON TRACK$160 million into the Affordable Housing Trust Fund over 10 years from FY2020; up to 6,500 certified affordable units by 2030 (November 2019 Action Plan)$142,494,769 budgeted through FY2028 (89%); 542 trust-fund apartments opened since April 2026; 2,367 units with money committed (about 36% of 6,500)2026-10-02
Will AdventHealth Winter Garden's tower expansion be completed in 2026 as promised?AdventHealth (for AdventHealth Winter Garden)Winter Garden, Florida (AdventHealth Winter Garden, 2000 Fowler Grove Blvd.)PENDING, ON TRACKThree-floor, ~105,000 sq ft tower expansion "completed in 2026" (May 2024 release); latest target "summer 2026"Labor and delivery opened Aug. 24, 2026; no record yet that the 40 progressive care beds are open or the expansion complete2026-10-06
Did the Orlando Housing Authority start building 41 homes at Carver Park in 2024, as it told HUD it would?Orlando Housing Authority (OHA), in its Moving to Work Annual Plans to HUD; partner: City of Orlando Community Redevelopment AgencyOrlando, Florida (Carver Park, HOPE VI homeownership phase)PENDING, OVERDUE
by about 21 months
Construction of 41 homes "to start in 2024" (FY2023 and FY2024 MTW plans; FY2024 plan submitted Jan. 13, 2023)Not started: OHA's FY2028 draft plan says it "has yet to begin", lists it "On Hold", and now anticipates up to 82 units in 20272026-10-07
Did FDOT finish rebuilding I-4 through Orlando in 2021, as promised?Florida Department of Transportation (FDOT), with its concessionaire I-4 Mobility PartnersOrlando, Florida (I-4 through Orlando, the I-4 Ultimate project)DELIVERED LATE
by about a year
"Expected to be substantially complete in 2021" (Federal Highway Administration project profile, archived Jan. 2015); contract date end of 2020"Substantially completed in 2022" (federal court findings); express lanes in use since February 2022; $125 million more to the state2026-10-07
Will Disney open Tropical Americas at Animal Kingdom in 2027, as it promised in 2024?The Walt Disney Company (Disney Experiences and Walt Disney Imagineering)Disney's Animal Kingdom, Walt Disney World Resort (Orange County, Florida)PENDING, ON TRACK2027 ("will open in 2027", Disney Parks Blog, Aug. 11, 2024, after D23)Not yet due; Disney's April 30, 2026 update and the Disney Experiences site still say 2027; the Walt Disney World calendar item now gives no year2026-10-08
Did Kissimmee widen Thacker Avenue by June 2025, as promised?City of KissimmeeKissimmee, Florida (Thacker Avenue, between Flora Boulevard and Osceola Parkway)PENDING, OVERDUE
by about 15 months
2025-06-30 (construction "7/1/2024" to "6/30/2025", the city's Jan. 2024 request to the Florida Senate)Not complete: still listed under Capital Projects (5-Yr Plan) in the city's Aug. 25, 2026 budget; no construction contract award found in 36 months of Commission records; the state's $250,000 was vetoed2026-10-08
Did the Orange County Library System finish building its Horizon West Branch in late 2025, as promised?Orange County Library SystemHorizon West, Orange County, Florida (the Horizon West Branch, Horizon West Regional Park)DELIVERED LATE
by about nine months
2025-12-31 ("Library construction is scheduled for completion in late 2025", the library system at the groundbreaking, Nov. 13, 2024)2026-10-10: the branch opened at its announced grand opening ("Opened on October 10, 2026", the library system; News 6 the same day); $21,978,082 of the $27,275,000 approved budget spent as of the October 2026 board packet2026-10-12
Did Seminole County open Fire Station 39 in late 2024, as promised?Seminole County (Seminole County Fire Department)Sanford, Seminole County, Florida (Fire Station 39, 5639 First Street at Orange Boulevard)DELIVERED LATE
by about 13 months
2024-12-31 ("Slated to open in late 2024", the county's groundbreaking release, Sept. 19, 2023)2026-02-04: grand opening ("Seminole County has officially opened Fire Station 39", county story stamped Feb. 12, 2026); a January 2026 settlement covered the builder's "request for an extension of time and additional fees"; final construction contract $8,355,227.742026-10-13
Did the Greater Orlando Aviation Authority start renovating Terminals A and B in 2025, as promised?Greater Orlando Aviation Authority (GOAA)Orlando, Florida (Orlando International Airport: Terminals A and B, and restrooms at all four airsides)PENDING, OVERDUE
by about nine months
2025-12-31 ("Construction is scheduled to begin in 2025 with substantial completion in 2027", GOAA release, Jan. 13, 2025)Not started in the records read: GOAA's pages now give construction starts of Winter 2026 (restrooms), 2027 (Airsides 1 and 3) and 2028 (landside levels), with substantial completion in 2029-2030; program cost $351 million2026-10-13
Did Osceola County finish its four priority road projects by 2025, as it said in 2021?Osceola CountyOsceola County, Florida (Poinciana Boulevard, Simpson Road, Boggy Creek Road and Partin Settlement Road)PENDING, OVERDUE
by about nine and a half months
2025-12-31 ("with all projects expected to be complete by 2025", the county's news release of Feb. 5, 2021)1 of 4 complete: Simpson Road finished in three segments, the last celebrated Oct. 12, 2026; Poinciana Boulevard, Boggy Creek Road and Partin Settlement Road in construction (Partin's schedule ends construction in the first quarter of 2027)2026-10-13
DELIVERED ON TIMEDELIVERED LATE DELIVERED SMALLERPENDING, ON TRACK PENDING, OVERDUEABANDONED

The entries

DELIVERED LATE (by about 13 months)

Did Seminole County open Fire Station 39 in late 2024, as promised?

Seminole County (Seminole County Fire Department) · Sanford, Seminole County, Florida (Fire Station 39, 5639 First Street at Orange Boulevard) · last checked 2026-10-13

The county's press release for the groundbreaking survives as reprinted by Fire Apparatus & Emergency Equipment magazine, under "PRESS RELEASE" and credited "(Source: Seminole County Fire Department)" . It said:

Read the full entry →

PENDING, OVERDUE (by about nine and a half months)

Did Osceola County finish its four priority road projects by 2025, as it said in 2021?

Osceola County · Osceola County, Florida (Poinciana Boulevard, Simpson Road, Boggy Creek Road and Partin Settlement Road) · last checked 2026-10-13

Osceola County's release PR21-18, "Osceola County Opens Cross Prairie Parkway", is dated February 5, 2021 . It announced the opening of Cross Prairie Parkway, then named the county's other priority roads:

Read the full entry →

PENDING, ON TRACK

Will Disney open Tropical Americas at Animal Kingdom in 2027, as it promised in 2024?

The Walt Disney Company (Disney Experiences and Walt Disney Imagineering) · Disney's Animal Kingdom, Walt Disney World Resort (Orange County, Florida) · last checked 2026-10-08

Disney calls Tropical Americas "a new land coming to Disney's Animal Kingdom" . Its 2024 post put the work on "this new 11-acre section of the park" . The Walt Disney World calendar page now names the land's two rides, "Antonio's Fiesta de Encanto" and "Indiana Jones and the Myth of the Jade…

Read the full entry →

PENDING, OVERDUE (by about 21 months)

Did the Orlando Housing Authority start building 41 homes at Carver Park in 2024, as it told HUD it would?

Orlando Housing Authority (OHA), in its Moving to Work Annual Plans to HUD; partner: City of Orlando Community Redevelopment Agency · Orlando, Florida (Carver Park, HOPE VI homeownership phase) · last checked 2026-10-07

The homes are the unbuilt homeownership phase of OHA's HOPE VI development at Carver Park: in 2018 OHA described "the 82 homeownership units that have not been developed at Carver Park" . Its partner is the City of Orlando's Community Redevelopment Agency (CRA) . In November 2018, OHA wrote, it…

Read the full entry →

DELIVERED LATE (by about a year)

Did FDOT finish rebuilding I-4 through Orlando in 2021, as promised?

Florida Department of Transportation (FDOT), with its concessionaire I-4 Mobility Partners · Orlando, Florida (I-4 through Orlando, the I-4 Ultimate project) · last checked 2026-10-07

The court called I-4 Ultimate "the state's most costly road project ever" . In the court's words, "Since February 2022, Central Florida drivers have benefited from the new I-4 express lanes running through Orlando."

Read the full entry →

PENDING, ON TRACK

Will AdventHealth Winter Garden's tower expansion be completed in 2026 as promised?

AdventHealth (for AdventHealth Winter Garden) · Winter Garden, Florida (AdventHealth Winter Garden, 2000 Fowler Grove Blvd.) · last checked 2026-10-06

On May 15, 2024, AdventHealth announced that "A major expansion at AdventHealth Winter Garden will add three floors to the hospital's patient tower and bring additional women's services to West Orange County" . The release stated its purpose: "This $145 million investment will address the…

Read the full entry →

PENDING, ON TRACK

Is Orange County putting the $160 million it promised in 2019 into its affordable housing trust fund?

Orange County Government (Mayor Jerry L. Demings's Housing for All Task Force; accepted by the Board of County Commissioners) · Orange County, Florida · last checked 2026-10-02

The homes the money was meant to produce are a different picture. The 2019 plan said: "Up to 6,500 certified affordable units will be produced by 2030 as a result of this committed local funding." In August 2026 the county reported that "four affordable apartment communities supported by the Trust…

Read the full entry →

PENDING, OVERDUE

Will downtown Orlando's Westcourt district be complete by March 2027, as its developers promised in 2024?

SED Development, JMA Ventures and Machete Group (the developers), with the Orlando Magic · Downtown Orlando, Florida (the block beside the Kia Center) · last checked 2026-10-01

In April 2024 three developers announced that their sports and entertainment district "to be developed on the 8.5-acre block adjacent to the Kia Center in downtown Orlando has been given final approval by the City of Orlando" . The developers were "SED Development, LLC, JMA Ventures, LLC, and…

Read the full entry →

PENDING, ON TRACK

Is CFX on course to build the Poinciana Parkway extension in the time it promised in 2024?

Central Florida Expressway Authority (CFX) · Poinciana, Osceola County, Florida (Orlando metro) · last checked 2026-09-30

In May 2024 the Central Florida Expressway Authority (CFX) said its new five-year work plan would "Deliver the SR 538 Poinciana Parkway Extension" along with three other expressway projects "through year eight of the fifteen-year planning period" . The extension is a "3.1-mile extension" in "two…

Read the full entry →

PENDING, ON TRACK

Is Orange County's $560 million convention center expansion on course to finish in 2029, as promised?

Orange County, Florida, through the Orange County Convention Center (OCCC) · Orlando, Florida (International Drive) · last checked 2026-09-29

In March 2025 the Orange County Convention Center (OCCC) said construction on its Grand Concourse Expansion "will begin in 2026 and is expected to finish in 2029" . On March 10, 2026 the Board of County Commissioners approved a guaranteed maximum price for the construction needed to complete the…

Read the full entry →

PENDING, OVERDUE (by eight months and 28 days)

Did OUC retire its Stanton Unit 1 coal plant by 2025, as its board voted in 2021?

Orlando Utilities Commission (OUC), Board of Commissioners · Orlando, Florida · last checked 2026-09-28

In December 2021 the board of the Orlando Utilities Commission (OUC) approved retiring Unit 1, a coal-fired unit, by no later than 2025 . OUC's 2022 plan said it would "retire" the unit; since 2023 its plans have said it will be placed "in cold shutdown" . A U.S. Department of Energy (DOE) order…

Read the full entry →