Will downtown Orlando's Westcourt district be complete by March 2027, as its developers promised in 2024?

The Roadmap Reckoner · Downtown Orlando, Florida (the block beside the Kia Center) · last checked 2026-10-01

VerdictPENDING, OVERDUE
PromiserSED Development, JMA Ventures and Machete Group (the developers), with the Orlando Magic
PlaceDowntown Orlando, Florida (the block beside the Kia Center)
PromisedGroundbreaking late 2024; completion by March 2027 (developers' April 2024 release)
Delivered / statusNot started: none of six City of Orlando permit applications issued (all Open); a developer now cites 2028 delivery
Last checked2026-10-01

Verdict: PENDING, OVERDUE, by about 21 months. In April 2024 the developers said that construction "is set to break ground in late 2024" and that the district "is scheduled for completion by March 2027" [C1, C2]. Reading "late 2024" as by the end of 2024, the start is about 1 year and 9 months late at this entry's last check. At that check, none of the project's six building, foundation and engineering applications had been issued on the City of Orlando's permit records: each is "Open", with no issue date [C10, C11, C12, C13, C14, C15]. The completion date has not arrived. One of the developers now gives "our projected 2028 delivery", in a statement quoted by Spectrum News 13 [C17].

In April 2024 three developers announced that their sports and entertainment district "to be developed on the 8.5-acre block adjacent to the Kia Center in downtown Orlando has been given final approval by the City of Orlando" [C1]. The developers were "SED Development, LLC, JMA Ventures, LLC, and Machete Group, Inc." [C1]. The block is "bounded by W. Church Street, Division Avenue, W. Central Boulevard, and S. Hughey Avenue" [C4]. The release carried a statement from the Orlando Magic's CEO that speaks of "this joint venture with the DeVos Family and the Orlando Magic" [C1]. The district is now called Westcourt Orlando [C6, C8].

Last checked: October 1, 2026.

The promise

The developers' release, issued by JMA Ventures through GlobeNewswire, is dated April 22, 2024 [C1, C5]. It said:

"Construction of the 900,000 square-foot mixed-use project is set to break ground in late 2024." [C1]

"The sports and entertainment district is scheduled for completion by March 2027 and projected to create 3,400 jobs." [C2]

The release described the project as "featuring a full-service 260-key hotel, 270 residential units, a 3,500-capacity live entertainment venue, Class-A office space, and a variety of dining and shopping options" [C3]. It also listed "a 1,140-stall parking garage" and a 1.5-acre outdoor green space [C3].

Timeline

What changed, and why, in the record's own words

What it costs

What to watch

What this entry did not check

Sources

  1. C1 https://www.globenewswire.com/news-release/2024/04/22/2867172/0/en/Downtown-Orlando-Sports-and-Entertainment-District-Approved-to-Begin-8-5-Acre-Block-Development.html
  2. C2 https://www.globenewswire.com/news-release/2024/04/22/2867172/0/en/Downtown-Orlando-Sports-and-Entertainment-District-Approved-to-Begin-8-5-Acre-Block-Development.html
  3. C3 https://www.globenewswire.com/news-release/2024/04/22/2867172/0/en/Downtown-Orlando-Sports-and-Entertainment-District-Approved-to-Begin-8-5-Acre-Block-Development.html
  4. C4 https://www.globenewswire.com/news-release/2024/04/22/2867172/0/en/Downtown-Orlando-Sports-and-Entertainment-District-Approved-to-Begin-8-5-Acre-Block-Development.html
  5. C5 https://www.globenewswire.com/news-release/2024/04/22/2867172/0/en/Downtown-Orlando-Sports-and-Entertainment-District-Approved-to-Begin-8-5-Acre-Block-Development.html
  6. C6 https://pressroom.grupoacs.com/en/news/turner-selected-for-westcourt-orlando-mixed-use-development
  7. C7 https://pressroom.grupoacs.com/en/news/turner-selected-for-westcourt-orlando-mixed-use-development
  8. C8 https://jmaventuresllc.com/portfolio/westcourt-orlando/
  9. C9 https://jmaventuresllc.com/portfolio/westcourt-orlando/
  10. C10 https://data.cityoforlando.net/resource/ryhf-m453.json
  11. C11 https://data.cityoforlando.net/resource/ryhf-m453.json
  12. C12 https://data.cityoforlando.net/resource/ryhf-m453.json
  13. C13 https://data.cityoforlando.net/resource/ryhf-m453.json
  14. C14 https://data.cityoforlando.net/resource/ryhf-m453.json
  15. C15 https://data.cityoforlando.net/resource/ryhf-m453.json
  16. C16 https://data.cityoforlando.net/resource/ryhf-m453.json
  17. C17 https://mynews13.com/fl/orlando/news/2026/02/27/westcourt-construction-behind-schdeule
  18. C18 https://www.growthspotter.com/2026/03/02/construction-underway-at-creative-village-westcourt-delayed/
  19. C19 https://www.downtownorlando.com/files/a623853b-2702-4b75-8438-411d9909617d/26_DDB_MajorDevelopmentProfile-web.pdf
  20. C20 https://www.downtownorlando.com/files/a623853b-2702-4b75-8438-411d9909617d/26_DDB_MajorDevelopmentProfile-web.pdf
  21. C21 https://www.downtownorlando.com/files/sharedassets/downtown/v/1/cra/meeting-minutes-amp-agendas/cra-advisory-board-agenda-august-27-2025.pdf
  22. C22 https://www.downtownorlando.com/files/sharedassets/downtown/v/1/cra/meeting-minutes-amp-agendas/cra-advisory-board-agenda-october-22-2025-2.pdf
  23. C23 Computed: C21 + C22 ($1,700,000 + $800,000 = $2,500,000)
  24. C25 https://mynews13.com/fl/orlando/news/2025/03/13/westcourt-orlando-to-break-ground-this-fall-
  25. C26 Computed: C10 + C11 + C12 (16,500,000 + 22,800,728 + 131,579,843 = 170,880,571)