Did the Greater Orlando Aviation Authority start renovating Terminals A and B in 2025, as promised?

The Roadmap Reckoner · updated 2026-11-04

PENDING, OVERDUE by about ten months

What happenedNot started in the records we found: GOAA's pages now give construction starts of Winter 2026 (restrooms), 2027 (Airsides 1 and 3) and 2028 (landside levels), with substantial completion in 2029-2030; program cost $351 million
Promised2025-12-31 ("Construction is scheduled to begin in 2025 with substantial completion in 2027", GOAA release, Jan. 13, 2025)
Who promisedGreater Orlando Aviation Authority (GOAA)
WhereOrlando, Florida (Orlando International Airport: Terminals A and B, and restrooms at all four airsides)

Verdict: PENDING, OVERDUE, by about ten months. In January 2025 the Greater Orlando Aviation Authority (GOAA) said, in a release on Orlando International Airport's website, that it "is moving forward with plans to refurbish the interiors in Terminals A & B and upgrade restrooms at all four airsides", and that "Construction is scheduled to begin in 2025 with substantial completion in 2027." [1] Reading "begin in 2025" as by the end of 2025, the start is 10 months and 4 days late as of November 4, 2026 [1]. In GOAA's construction report for October 2026, "Restroom design and logistics planning are in progress" and "subcontractor trade procurement is in progress", and on Airsides 1 and 3 "The contractor has completed and submitted 30% design documents." [20, 21] The third piece, the landside Levels 2 and 3 of Terminals A and B, is "included in the future program" [15]. GOAA's pages now give substantial completion in 2029 and 2030 [15, 16].

The promise

GOAA's release "GOAA Celebrates 2024 Awards, Looks Ahead to 2025 Projects", dated January 13, 2025, under the heading "TERMINAL A & B RENOVATIONS" [1]:

"The Aviation Authority is moving forward with plans to refurbish the interiors in Terminals A & B and upgrade restrooms at all four airsides. The scope will consist of the design and construction of Landside and Airside interior refurbishment, and will include new flooring, new wall finishes, new ceilings with lighting improvements, and new restrooms. Construction is scheduled to begin in 2025 with substantial completion in 2027." [1]

Timeline

What changed, and why

What it cost

What is still open

Sources

  1. 1. flymco.com › goaa celebrates 2024 awards looks ahead to 2025 projects
  2. 2. netapps.ocfl.net
  3. 3. netapps.ocfl.net
  4. 4. flymco.com › goaa board welcomes lance lyttle new airport ceo
  5. 5. downloads.ctfassets.net › 20260318 Agenda Board Packet Final v3
  6. 6. assets.ctfassets.net › Revised Board Agenda Packet 2025 10 15.v3
  7. 7. assets.ctfassets.net › Revised Agenda Packet 20251119 v2 1
  8. 8. assets.ctfassets.net › Board Agenda Packet 2026 01 21 Final
  9. 9. assets.ctfassets.net › Revised Board Agenda Packet 20260520 Final
  10. 10. assets.ctfassets.net › Board Meeting Packet 20260415 Revised v3
  11. 11. downloads.ctfassets.net › REVISED Board Agenda Packet 20260916 v3
  12. 12. assets.ctfassets.net › Committee Meeting Packet 20260916
  13. 13. downloads.ctfassets.net › Board Agenda Packet 20260218 Final REVISED v3
  14. 14. downloads.ctfassets.net › Agenda Packet 12 17 2025 Revised v4
  15. 15. flymco.com › current north terminal renovations
  16. 16. flymco.com › north terminal renovations
  17. 17. flymco.com › goaa board approves new investments to elevate mco
  18. 18. netapps.ocfl.net
  19. 19. assets.ctfassets.net › Committee Meeting Minutes Packet 20260520
  20. 20. downloads.ctfassets.net › 20261021 Board Agenda Packet Final Second Revised
  21. 21. downloads.ctfassets.net › 20261021 Board Agenda Packet Final Second Revised
  22. 22. downloads.ctfassets.net › Construction Agenda R1 20261103

Updates and corrections

Corrected 20 October 2026: two lines, on the restroom change orders and on the restroom award vote, were extended with a second GOAA record that had been saved as a scan without a text layer: the minutes of the Construction Finance Oversight Committee's meeting of March 24, 2026. The verdict and every date in the timeline are unchanged.

Re-checked November 4, 2026. GOAA's construction report for the October 2026 Board, posted after this page's previous update, says of the restrooms: "Restroom design and logistics planning are in progress. The 100% design documents are in progress, and subcontractor trade procurement is in progress. The project is on schedule." [20] The restroom contract is unchanged at "Current Contract $71,970,777.00" and 1344 days, with completion "01/30/29", and the report shows "Paid To Date Thru PA # 14 $4,261,791.84" [20]. Of Airsides 1 and 3 it says "The contractor has completed and submitted 30% design documents." [21] GOAA's project pages, read again on November 4, give the same starts and completions as on October 13 [15, 16]. The Construction Committee's change-order agenda for November 3, 2026 lists a change order of $152,497.00 on the Airsides 1 and 3 contract, for replacing the public address system at Airside 1, and two restroom change orders of $0.00, each with zero days of time impact [22]. That is an agenda; we have not looked at its result. The records we have seen still show no construction started on any of the three pieces. The verdict is unchanged; the delay is counted to November 4, 2026.