Did Orlando finish all 150 Palm Gardens apartments by the end of 2024, as the city said?
The Roadmap Reckoner · Orlando, Orange County, Florida (Palm Gardens Orlando, 929 West Colonial Drive) · last checked 2026-10-20
| Verdict | DELIVERED LATE, by about four months |
| Promiser | City of Orlando (Housing and Community Development; Palm Gardens Orlando Apartments, LLC) |
| Place | Orlando, Orange County, Florida (Palm Gardens Orlando, 929 West Colonial Drive) |
| Promised | End of 2024 ("All 150 units at Palm Gardens Orlando are anticipated to be completed by the end of the year", the city's release of May 29, 2024) |
| Delivered / status | May 2025: the second phase's building permit shows a certificate-of-occupancy date of May 6, 2025 (126 days after Dec. 31, 2024), and the city held its ceremony on May 28, 2025; the city's grant contract had already moved completion to June 30, 2025 |
| Last checked | 2026-10-20 |
Verdict: DELIVERED LATE, by about four months. In its release for the first phase opening, the City of Orlando said: "All 150 units at Palm Gardens Orlando are anticipated to be completed by the end of the year" [C1]. The release is dated May 29, 2024 [C1b], so the year was 2024. The second phase's building permit shows a certificate-of-occupancy date of May 6, 2025 [C16], which is 126 days after December 31, 2024 [the trace]. The city held its ceremony for the second phase on May 28, 2025 [C18c], 148 days after it [the trace]. The city's release for that day says the ceremony would "celebrate completion of the second and final phase of Palm Gardens Orlando" [C18b].
The city's own grant contract had already moved its completion date to June 30, 2025, five and a half months before the promise was made [C13, C11]. Measured against that date, the work finished 55 days early [the trace]. So the entry is late against what the city told the public, and early against what the city's contract required.
Last checked: October 20, 2026.
- The promise. All 150 units by the end of 2024 [C1].
- The record since. The contract's dates were extended in December 2023 [C13]. The city's release was not changed; its sentence reads the same in the last Internet Archive capture, dated July 12, 2026 [C1c, C1d].
- The delivery. Phase two: a certificate-of-occupancy date of May 6, 2025 [C16] and a city ceremony on May 28, 2025 [C18c].
- The cost. The city's grant was $4,159,300 [C6]. The release called it "more than $4 million" [C3].
The promise
The City of Orlando's release, "City Celebrates Phase One Grand Opening of Palm Gardens Orlando", said:
"All 150 units at Palm Gardens Orlando are anticipated to be completed by the end of the year, with 149 efficiency and one-bedroom apartments reserved for residents with incomes at or less than 80% of the Area Median Income (AMI)" [C1]
The page reads "Last updated on May 29, 2024" [C1b]. The same release said the city would "celebrate the completion of the first 95 units of Palm Gardens Orlando" [C2]. The conversion is of the former Ambassador Hotel at 929 West Colonial Drive, using the city's "Accelerate Orlando" money [the trace].
Before the promise
- October 24, 2022. City Council took up the grant agreement. Its cover page reads "For Meeting of: October 24, 2022" [C5]. The council agenda summary described two phases: "Phase 1 will be completed by December 31, 2023 and will consist of approximately ninety-two (92) apartments" [C5b], and "Phase 2 will be completed by December 31, 2024, and will consist of approximately fifty-eight (58) affordable housing apartments, plus certain amenities." [C5c]
- The 2022 contract dates. Among the agreement's conditions for paying out the city's second allotment was "Phase 2 Project Completion no later than December 31, 2024, as evidenced by the issuance of a certificate of occupancy or certificate of completion." [C8] Its performance benchmark in Section 7.B reads: "Phase 1 Completion shall be no later than November 30, 2023, and Project Completion shall be on or before December 31, 2024." [C9] The record therefore gives Phase 1 two dates: December 31, 2023 in the agenda summary [C5b], and November 30, 2023 in Section 7.B [C9]. The 2023 amendment later describes the old Phase 1 date as "December 31, 2023" [C13b]. The record read does not settle which date governed [the trace].
- The 2022 budget. "The total project budget is $15,140,277. Owner equity will provide $3,250,000. Additional funding sources include bank debt in the amount of $6,230,977. The owner has requested $4,159,300 in Accelerate Orlando funding to fill their financing gap." [C6] The remainder came from impact-fee waivers: "for the remaining balance of $1,500,000." [C6b]
Timeline
- December 11, 2023. The amendment went to City Council ("For Meeting of: December 11, 2023" [C11]). Its stated reason: "The owner has determined that construction activities will need more time due to some construction material limitations as well as previous Covid related delays." [C12]
- It would "change the date for Phase 2 completion and Project completion from December 31, 2024 to June 30th, 2025." [C13]
- The owner's updated schedule showed "Phase I Completion will occur no later than June 30, 2024, and Phase 2 Completion and Project Completion no later than June 30, 2025." [C14]
- January 23, 2024. The application for the phase-two building permit, BLD2024-10669, was filed [C16b].
- May 29, 2024. The city's release made the promise. By then council had approved the June 30, 2025 date 170 days earlier [C13, C1b, the trace]. The release page as read on October 19, 2026 does not state the contract's June 30, 2025 date [the trace].
- July 3, 2024. The phase-one permit, BLD2023-14189, shows a certificate-of-occupancy date of July 3, 2024 [C15].
- December 31, 2024. The promised date passed. The phase-two permit had not been issued yet [C16c].
- January 19, 2025. The city's Livable Orlando report said "Palm Gardens Affordable Housing – PHASE ONE COMPLETED." [C17, C17b] A later page of the same report still said the building "will provide 150 apartments once completed in 2024" [C17c].
- February 3, 2025. The phase-two building permit was issued [C16c]. That is 377 days after filing [the trace].
- May 6, 2025. The phase-two permit shows its certificate-of-occupancy date [C16].
- May 28, 2025. The city's release for the second ceremony reads "Last updated on May 28, 2025" [C18]. It gives the event as "Wednesday, May 28, 2025 10 a.m." [C18c].
What changed, and why, in the record's own words
- The date in the contract. Section 7.B of the agreement said "Phase 1 Completion shall be no later than November 30, 2023, and Project Completion shall be on or before December 31, 2024." [C9] The amendment replaced Section 7.B with one that reads "Project Completion shall be on or before June 30, 2025." [C14b]
- The reason. "construction material limitations as well as previous Covid related delays." [C12]
- The date in the public release. The release's "by the end of the year" [C1] stayed in place. It is the same in all 8 Internet Archive captures from September 14, 2024 to July 12, 2026 [C1c, C1d].
- The finish. The city called the May 2025 event the "completion of the second and final phase of Palm Gardens Orlando" [C18b].
What it cost
- The city's grant: $4,159,300 [C6], which the city's release described as "more than $4 million" [C3].
- The 2022 project budget: $15,140,277 [C6]. Its four sources are the owner's $3,250,000, the bank's $6,230,977, the city's $4,159,300 and $1,500,000 in impact-fee waivers [C6, C6b]. They add up to the total [the trace].
- Permit valuations are $3,000,000 for phase one [C15b] and $2,400,000 for phase two [C16b]. They are the permit applications' estimates, not the project's cost [the trace].
What is still open
- When the 30-year affordability period began. The city's release says it starts "from the date all completed units have been leased." [C4]
- How the amended deadline for phase one compared with the record. The original phase-one date is itself stated two ways (see the Before the promise section). The amended phase-one date was June 30, 2024 [C14b]; the phase-one permit's certificate-of-occupancy date is July 3, 2024 [C15]. The dataset leaves the meaning of its COO Date column blank [C16d]. This entry does not treat the three days as a breach.
What this entry did not check
- Whether the city released its money on schedule. The escrow records were not read [the trace].
- The Affordability Certificate and the owner's annual reports were not found in any public record read [the trace].
- Current rents. The 2022 agreement set rent caps, and One Stop Housing's page today lists higher rents. The caps move each year with a state chart that could not be read, so this entry draws no conclusion [the trace].
- The recorded copy of the 2023 amendment in the county's Official Records, and the city's permit portal (temporary certificates), were not searched [the trace].
Sources
- C1 https://www.orlando.gov/News/Press-Releases/2024-Press-Releases/City-Celebrates-Phase-One-Grand-Opening-of-Palm-Gardens-Orlando
- C1b https://www.orlando.gov/News/Press-Releases/2024-Press-Releases/City-Celebrates-Phase-One-Grand-Opening-of-Palm-Gardens-Orlando
- C1c https://web.archive.org/web/20260712021624/https://www.orlando.gov/News/Press-Releases/2024-Press-Releases/City-Celebrates-Phase-One-Grand-Opening-of-Palm-Gardens-Orlando
- C1d https://web.archive.org/cdx/search/cdx?url=www.orlando.gov/News/Press-Releases/2024-Press-Releases/City-Celebrates-Phase-One-Grand-Opening-of-Palm-Gardens-Orlando&collapse=digest
- C2 https://www.orlando.gov/News/Press-Releases/2024-Press-Releases/City-Celebrates-Phase-One-Grand-Opening-of-Palm-Gardens-Orlando
- C3 https://www.orlando.gov/News/Press-Releases/2024-Press-Releases/City-Celebrates-Phase-One-Grand-Opening-of-Palm-Gardens-Orlando
- C4 https://www.orlando.gov/News/Press-Releases/2024-Press-Releases/City-Celebrates-Phase-One-Grand-Opening-of-Palm-Gardens-Orlando
- C5 https://portal.laserfiche.com/Portal/DocView.aspx?id=988408&repo=r-b158fc8c
- C5b https://portal.laserfiche.com/Portal/DocView.aspx?id=988408&repo=r-b158fc8c
- C5c https://portal.laserfiche.com/Portal/DocView.aspx?id=988408&repo=r-b158fc8c
- C6 https://portal.laserfiche.com/Portal/DocView.aspx?id=988408&repo=r-b158fc8c
- C6b https://portal.laserfiche.com/Portal/DocView.aspx?id=988408&repo=r-b158fc8c
- C8 https://portal.laserfiche.com/Portal/DocView.aspx?id=988408&repo=r-b158fc8c
- C9 https://portal.laserfiche.com/Portal/DocView.aspx?id=988408&repo=r-b158fc8c
- C11 https://portal.laserfiche.com/Portal/DocView.aspx?id=998664&repo=r-b158fc8c
- C12 https://portal.laserfiche.com/Portal/DocView.aspx?id=998664&repo=r-b158fc8c
- C13 https://portal.laserfiche.com/Portal/DocView.aspx?id=998664&repo=r-b158fc8c
- C13b https://portal.laserfiche.com/Portal/DocView.aspx?id=998664&repo=r-b158fc8c
- C14 https://portal.laserfiche.com/Portal/DocView.aspx?id=998664&repo=r-b158fc8c
- C14b https://portal.laserfiche.com/Portal/DocView.aspx?id=998664&repo=r-b158fc8c
- C15 https://data.cityoforlando.net/resource/ryhf-m453.json
- C15b https://data.cityoforlando.net/resource/ryhf-m453.json
- C16 https://data.cityoforlando.net/resource/ryhf-m453.json
- C16b https://data.cityoforlando.net/resource/ryhf-m453.json
- C16c https://data.cityoforlando.net/resource/ryhf-m453.json
- C16d https://data.cityoforlando.net/api/views/ryhf-m453.json
- C17 https://www.orlando.gov/files/sharedassets/public/v/1/departments/edv/city-planning/livable-orlando-2024-implementation-highlights-report.pdf
- C17b https://www.orlando.gov/files/sharedassets/public/v/1/departments/edv/city-planning/livable-orlando-2024-implementation-highlights-report.pdf
- C17c https://www.orlando.gov/files/sharedassets/public/v/1/departments/edv/city-planning/livable-orlando-2024-implementation-highlights-report.pdf
- C18 https://www.orlando.gov/News/Press-Releases/2025-Press-Releases/Phase-Two-Grand-Opening-of-Palm-Gardens-Orlando-Apartments
- C18b https://www.orlando.gov/News/Press-Releases/2025-Press-Releases/Phase-Two-Grand-Opening-of-Palm-Gardens-Orlando-Apartments
- C18c https://www.orlando.gov/News/Press-Releases/2025-Press-Releases/Phase-Two-Grand-Opening-of-Palm-Gardens-Orlando-Apartments
← All Reckoner entries